Taoyuan Aerotropolis Project
2009/1/23
“International Airport Park Development Act” released
2016/4/29~5/1
MOTC held “Taoyuan International Airport and the Adjacent Designated Area Plan (Phase I)FormalPublic Hearings”
2018/3/27
Urban Planning Commission, Ministry of the Interior approved the “Taoyuan Aerotropolis Project”
2018/10/11
Start the examination and appraisal of aboveground objects
2019/7/15~8/24
Conduct land negotiation and purchase meeting
2019/9/17~10/28
Completion of the public hearing on the acquisition of land sections
2020/3/25
The third runway of Taoyuan International Airport passed the environmental assessment
2020/4/29
The land expropriation group meeting of the Ministry of Interior has examined and approved the Taoyuan Aerotropolis sectional expropriation plan
2020/6/22~8/5
Conduct negotiation and purchase meeting of aboveground objects
2020/11/9~12/9
Announcement of land sectional expropriation
2021/2/26~3/12
Public hearing on sectional expropriation of aboveground objects in priority relocation areas
2021/5/31~6/30
Announcement of sectional expropriation of aboveground objects in the Industry Priority Area
2021/5/31~10/31
Relocation of aboveground objects in the Industry Priority Area
2021/7/7
The Land Expropriation Panel of the Ministry of Interior deliberated and approved the expropriation of aboveground improvements for the Taoyuan Airport Park and other relocation areas in phase I
2021/7/15~8/13
To handle the notice of expropriation of the aboveground sections of the Taoyuan Airport Park and other relocation areas in phase I
2022 Q2
Initiate investment promotion in Industry Priority Area
2023 Q2
Completion of the public works in Industry Priority Area
2023 Q2
Land delivery will be carried out in Industry Priority Area, and manufacturers will start to move in
2024 Q4
Conduct the relocation of the entire district
2024 Q4
Conduct district-wide public projects
“International Airport Park Development Act” released
2016/4/29~5/1
MOTC held “Taoyuan International Airport and the Adjacent Designated Area Plan (Phase I)FormalPublic Hearings”
2018/3/27
Urban Planning Commission, Ministry of the Interior approved the “Taoyuan Aerotropolis Project”
2018/10/11
Start the examination and appraisal of aboveground objects
2019/7/15~8/24
Conduct land negotiation and purchase meeting
2019/9/17~10/28
Completion of the public hearing on the acquisition of land sections
2020/3/25
The third runway of Taoyuan International Airport passed the environmental assessment
2020/4/29
The land expropriation group meeting of the Ministry of Interior has examined and approved the Taoyuan Aerotropolis sectional expropriation plan
2020/6/22~8/5
Conduct negotiation and purchase meeting of aboveground objects
2020/11/9~12/9
Announcement of land sectional expropriation
2021/2/26~3/12
Public hearing on sectional expropriation of aboveground objects in priority relocation areas
2021/5/31~6/30
Announcement of sectional expropriation of aboveground objects in the Industry Priority Area
2021/5/31~10/31
Relocation of aboveground objects in the Industry Priority Area
2021/7/7
The Land Expropriation Panel of the Ministry of Interior deliberated and approved the expropriation of aboveground improvements for the Taoyuan Airport Park and other relocation areas in phase I
2021/7/15~8/13
To handle the notice of expropriation of the aboveground sections of the Taoyuan Airport Park and other relocation areas in phase I
2022 Q2
Initiate investment promotion in Industry Priority Area
2023 Q2
Completion of the public works in Industry Priority Area
2023 Q2
Land delivery will be carried out in Industry Priority Area, and manufacturers will start to move in
2024 Q4
Conduct the relocation of the entire district
2024 Q4
Conduct district-wide public projects