About the plan
-
2021
2021.02.26 - 2021.03.12 Public hearing on sectional expropriation of aboveground objects in priority relocation areas.
-
2020
2020.03.25 The third runway of Taoyuan International Airport passed the environmental assessment.
2020.04.29 The land expropriation group meeting of the Ministry of Interior has examined and approved the Taoyuan Aerotropolis sectional expropriation plan.
2020.06.22 - 2020.08.05 Conduct negotiation and purchase meeting of aboveground objects.
2020.11.09 - 2020.12.09 Announcement of land sectional expropriation. -
2019
2019.07.16-08.24 Conduct land negotiation and purchase meeting.
2019.09.17-10.28 Completion of the public hearing on the acquisition of land sections. -
2018
2018.03.27 Urban Planning Commission, Ministry of the Interior approved the Taoyuan Aerotropolis Plan.
-
2017
2017.08.19-09.09 The Taoyuan Aerotropolis Urban Plan was re-exhibited and orientations held.
-
2016
2016.04.29-05.01 MOTC held “Taoyuan International Airport and the Adjacent Designated Area Plan (Phase I)FormalPublic Hearings” (6 hearings in total).
-
2015
2015.10.03-11.15 MOTC held “Taoyuan International Airport and the Adjacent Designated Area Plan (Phase I) Preliminary Public Hearings ” (24 hearings in total).
-
2014
2014.02.25 The Taoyuan Aerotropolis Urban Plan was re-exhibited
2014.07.29 Urban Planning Commission of the Ministry approved and finalized the Taoyuan Aerotropolis Urban Plan
2014.11.10 The Ministry of Interior sent the approved plan and schematics to MOTC and Taoyuan City Government. -
2013
2013.07.24 Taoyuan Aerotropolis Urban Plan was exhibited
2013.12.30 Urban Planning Commission of the Ministry of the Interior approved the Taoyuan Aerotropolis Plan -
2012
2012.09.18 Executive Yuan announced to launch the Taoyuan Aerotropolis Plan
2012.10.25 Taoyuan County Government established the Taoyuan Aerotropolis Promotion Committee